Quick Answer: What a Used Tower Crane Is Worth
A used tower crane for sale in the export market typically trades at 40 to 70 percent of new price, depending on age, working hours, mast section condition and documentation. A second hand tower crane with a complete maintenance log commands 10 to 15 percent more than the same machine with no history.
A 6015 class machine at three to five years old commonly sits between USD 30,000 and 55,000, against USD 65,000 to 105,000 new. A used 7020 at the same age sits between USD 50,000 and 85,000.
|
Class |
Typical model |
Age |
Used price (USD) |
Percent of new |
|
Light |
QTZ63 / 5013 |
3-5 years |
18,000 - 32,000 |
40 - 45% |
|
Mid |
QTZ80 / 6015 |
3-5 years |
30,000 - 55,000 |
45 - 55% |
|
Mid-heavy |
6018 / 6515 |
3-5 years |
38,000 - 62,000 |
45 - 52% |
|
Heavy |
QTZ160 / 7020 |
3-5 years |
50,000 - 85,000 |
45 - 55% |
|
Heavy |
QTZ160 / 7020 |
8-10 years |
28,000 - 48,000 |
25 - 32% |
|
Super-heavy |
QTZ250 / 7527 |
5-8 years |
90,000 - 140,000 |
40 - 50% |
Why the Used Market Is Priced by Rumour
New crane pricing follows a cost structure, and a competent buyer can reconstruct it. Used crane pricing follows whatever the last three similar machines sold for, which nobody publishes. Any used tower crane price you find published is a starting point for negotiation, not a market rate. That information gap is where money is made and lost.
Three structural problems make it worse. Working hours are rarely documented, because many machines run without a data logger. Repair history is held by the maintenance team, not the owner's accounts. And the machine's physical condition at the point of sale is often the best it has looked in five years, because it has been repainted.
None of this means the used market is a bad place to buy. For a rental fleet or a contractor with an in-house maintenance team, a well-chosen used unit delivers more lifting capacity per dollar than anything else available. It simply requires a process rather than a judgement call.
The Seven Factors That Actually Set the Price
Sellers talk about year of manufacture. Buyers should talk about these seven, in this order of influence.
|
Factor |
Weight in valuation |
What to measure |
Strong signal |
Weak signal |
|
Working hours and duty cycles |
25% |
Hour meter, data logger, project history |
Under 6,000 hours |
Meter replaced or disconnected |
|
Mast section condition |
20% |
Straightness, pin holes, chord corrosion |
Sections interchangeable, no ovality |
Mixed sections from different batches |
|
Slewing ring and drive |
15% |
Axial and radial clearance, backlash |
No detectable play, smooth rotation |
Visible play, grease leakage |
|
Wire rope and sheaves |
10% |
Broken wires, diameter loss, groove wear |
Within ISO 4309 discard limits |
Rope age unknown, sheaves grooved |
|
Structural welds |
10% |
Chord and batten welds, crack inspection |
Original welds, no repair |
Field repairs, hammered paint over cracks |
|
Documentation |
10% |
Load test record, maintenance log, manuals |
Complete history from commissioning |
"Papers lost" |
|
Model popularity in your market |
10% |
Local parts availability |
Common model, parts in stock |
Obsolete model, parts by special order |
Note the last factor. A common model in mediocre condition is often a better buy than a rare model in excellent condition, because the rare one converts every future repair into a three-month wait.
Used vs New Tower Cranes: The Full Comparison
The purchase price is one line in a longer table. This is the comparison that decides whether buying used is rational for your situation.
|
Dimension |
New tower crane |
Used tower crane |
Net effect |
|
Purchase price |
100% |
40 - 70% |
Used saves 30 - 60% upfront |
|
Lead time |
30 - 60 days production |
7 - 21 days from stock |
Used is faster |
|
Certification documents |
Full, model-specific |
Partial, often missing type test |
New is safer in regulated markets |
|
First-year maintenance |
Low, warranty covered |
Moderate to high, buyer-funded |
New is cheaper to run initially |
|
Spare parts risk |
Manufacturer current range |
Model may be obsolete |
New is lower risk |
|
Downtime from unknown faults |
Low |
Higher in year one |
New is more predictable |
|
Resale after 5 years |
45 - 55% of purchase |
25 - 35% of purchase |
Similar absolute loss |
|
Suitability |
Regulated markets, tenders requiring new equipment |
Rental fleets, repeat projects, markets without type approval |
Depends on use case |
The absolute depreciation is often close, which surprises buyers. A new 6015 at USD 85,000 loses about 45,000 over five years. A used 6015 bought at 45,000 loses about 15,000 over the same period. The used machine wins on capital efficiency and loses on predictability.
The Residual Value Curve
Selling prices decay in a predictable shape, and knowing the shape is how you avoid overpaying at year four.
|
Machine age |
Residual value (% of new) |
Annual loss |
Buyer profile |
|
1 - 2 years |
65 - 75% |
Steepest |
Buyers who want near-new without the price |
|
3 - 5 years |
45 - 55% |
Moderate |
Best value window for most fleets |
|
6 - 8 years |
32 - 40% |
Flattening |
Fleets with in-house workshops |
|
9 - 12 years |
20 - 28% |
Slow |
Budget projects, short remaining life |
|
Over 12 years |
12 - 20% |
Near flat |
Parts donors, low-rise work |
The three-to-five year window is the rational entry point for most buyers: the steepest depreciation has already been absorbed, and the machine is still in its first structural life. Below 20 percent residual, the purchase price stops being the main cost and the maintenance budget becomes decisive.
How to Inspect a Used Tower Crane: The 60-Point Check
Inspection is not a walk-around. It is six groups of measurements, each producing a number you can compare against a limit. Bring a tape, a straight edge, feeler gauges, a caliper and a torch.
|
Group |
Points |
What to check |
Reject if |
|
Structure |
12 |
Chord straightness, batten welds, corrosion depth, section interchangeability |
Straightness deviation above 1/1000 of length; any crack at chord-to-batten weld |
|
Connection |
10 |
Pin diameter, hole ovality, pin retention, bolt condition |
Hole clearance above 1 mm; pins with step wear |
|
Hoisting |
12 |
Rope condition, drum grooving, sheave wear, brake lining, gearbox oil |
Rope beyond ISO 4309 limits; brake lining under 50% |
|
Slewing |
8 |
Ring clearance, gear backlash, motor current, brake |
Detectable axial play; grease with metal particles |
|
Electrical |
10 |
Cable insulation, cabinet condition, limiter function, anemometer |
Limiter bypassed or uncalibrated; cracked insulation |
|
Documentation |
8 |
Load test, maintenance log, manuals, spare-part history |
No load test record for the last 24 months |
Two measurements deserve special attention because they predict the largest future costs.
Mast section straightness. Stand the section on a flat surface and measure deviation over its full length with a tensioned line. A deviation above 1/1000 means the section will not erect true, and mixing it into a tower accelerates pin wear on every section above it.
Pin hole ovality. Measure the hole in two directions with a caliper. New clearance is typically 0.1 to 0.3 mm. Above 1 mm, the tower develops play that shows up as erection difficulty and, in the worst case, as fatigue cracking at the connection.
Wire Rope: The Objective Discard Criteria
Wire rope is the one component where the decision can be made entirely on measurement, without judgement.
|
Rope type |
Broken wires in 6d length |
Broken wires in 30d length |
Other discard triggers |
|
Six-strand, single layer |
10% of outer wires |
20% of outer wires |
Diameter loss above 10%, severe corrosion |
|
Rotation-resistant |
5% of outer wires |
10% of outer wires |
Bird-caging, kinking, core protrusion |
|
Any type |
Any broken valley wire in a running rope |
- |
Heat damage, electric arc marks |
Replacement cost for a 6015 hoist rope is a few hundred to about USD 1,500 depending on length and construction, so this is not a reason to walk away. It is a reason to negotiate, and to check whether the sheaves that wore the rope are also worn.
Refurbishment Budget: What It Really Costs
Every used crane needs something. The useful discipline is to price the work before signing, so the negotiation reflects it.
|
Work item |
Typical cost (USD) |
Frequency on used units |
Priority |
|
Full wire rope replacement |
600 - 1,500 |
Common |
Safety critical |
|
Brake lining and adjustment |
200 - 600 |
Very common |
Safety critical |
|
Repaint, two-coat system |
1,500 - 4,000 |
Almost always |
Cosmetic and corrosion |
|
Mast section re-straightening |
300 - 800 per section |
Occasional |
Structural |
|
Slewing ring replacement |
3,000 - 8,000 |
Rare but decisive |
Structural |
|
Electrical cabinet overhaul |
800 - 2,500 |
Common on 8+ year units |
Reliability |
|
Limiter and anemometer replacement |
500 - 1,500 |
Common |
Compliance |
|
Cabin refurbishment |
400 - 1,200 |
Optional |
Operator acceptance |
A useful rule: assume 10 percent of the purchase price for a three-to-five year machine and 20 percent for anything over eight years. If the seller's price already reflects that, the deal is fair. If it does not, the number is your counter-offer.
Documentation: What a Used Crane Should Come With
A machine with papers is worth more than the same machine without them, in every market. The pack should contain eight items, and their absence is itself a negotiating point.
1.Original load test certificate, and any subsequent annual test records.
2.Maintenance log with dates, tasks and parts replaced.
3.Wire rope certificates for the rope currently fitted.
4.Limiter calibration record with the date and the technician.
5.Complete set of manuals: operation, maintenance, parts catalogue, wiring diagram.
6.Mast section and jib section numbering list, matching the physical markings.
7.Any repair or modification record, with drawings where structure was affected.
Item five is the one buyers underestimate. Without a wiring diagram, every electrical fault becomes an investigation, and a machine with an undocumented modification can cost more in diagnosis than it saved in price.
Three Refurbishment Levels and What They Mean
Sellers use the words loosely. These definitions are the ones worth writing into a contract.
|
Level |
What is done |
Typical price uplift |
Reasonable expectation |
|
As-is |
Cleaned and painted only |
Baseline |
Expect repairs in year one |
|
Workshop refurbished |
Rope, brakes, electrical, paint, limiter calibrated |
+10 to 18% |
Serviceable for normal duty |
|
Rebuilt |
Structural inspection, worn parts replaced, full load test, new documentation |
+25 to 40% |
Close to new reliability, documented |
"As-is, repainted" is the most common description in the market and the least informative. Ask which components were replaced and request the invoices; a refurbishment without parts invoices is a paint job.