Quick Answer: Time and Cost of Erecting a Tower Crane
Erecting a 6015 class tower crane to a 40 m free-standing height takes 2 to 3 days with a crew of four to six, plus one day for load testing and handover. Tower crane dismantling takes 2 to 3 days. Budget USD 3,000 to 9,000 for the erection labour and mobile crane, before foundation and transport.
|
Task |
Duration |
Crew |
Typical cost (USD) |
Governing constraint |
|
Foundation handover and survey |
0.5 day |
2 |
300 - 800 |
Concrete cure and anchor position tolerance |
|
Base section and first mast sections |
1 day |
4 - 6 |
1,200 - 3,000 |
Mobile crane capacity at radius |
|
Climbing to free-standing height |
0.5 - 1 day |
4 |
800 - 2,000 |
Wind, hydraulic system condition |
|
Jib, counter-jib and counterweight |
1 day |
5 - 7 |
1,500 - 3,500 |
Heaviest single component |
|
Rope reeving, electrical, limiter calibration |
0.5 day |
2 - 3 |
400 - 1,000 |
Certified electrician availability |
|
Load test and handover |
0.5 day |
3 |
300 - 900 |
Test weights on site |
|
Dismantling (reverse sequence) |
2 - 3 days |
4 - 6 |
3,000 - 8,000 |
Access, corrosion, fatigue |
Why Erection Planning Starts Before the Crane Is Ordered
Erection cost is decided at the specification stage, not on the day the mobile crane arrives. Three ordering decisions drive it: free-standing height, maximum component weight and jib length.
A crane ordered with eight extra mast sections needs a taller climbing sequence, a longer mobile crane boom and more transport volume. A jib split into more sections reduces the heaviest lift and allows a smaller mobile crane, at the cost of more assembly time. These trade-offs are cheap to make on paper and expensive to make on site.
The most common planning failure is ordering the machine to the building height and then discovering the site cannot accommodate the mobile crane at the required radius. A 100 t mobile crane needs a stable standing area roughly 8 by 10 m, and on tight urban sites that area is where the material laydown was planned.
Who Is Allowed to Erect a Tower Crane
Erection is a regulated activity in almost every market, and the rules share a common shape: a competent person, a written method statement, a risk assessment and a documented handover. The roles below are the minimum structure.
|
Role |
Responsibility |
Must be able to show |
|
Site controller |
Authorises the operation and controls access |
Site induction records, exclusion zone plan |
|
Erection supervisor |
Runs the sequence and signs the method statement |
Competency certificate, experience record |
|
Mobile crane operator |
Executes the lifts to the lift plan |
Licence for the crane class, lift plan briefing |
|
Slinger and riggers |
Attach and control loads |
Rigging certification |
|
Electrician |
Connects power, tests the safety circuit |
Electrical competency, test records |
|
Competent inspector |
Load tests and hands over |
Accreditation recognised in the jurisdiction |
In many countries the erection crew must be approved by the manufacturer or by a recognised body, and the machine's warranty may depend on it. Confirm this before appointing a local crew, because an unapproved erection can void both warranty and insurance.
Six Inputs Every Erection Plan Needs
A method statement is only as good as its inputs. These six are the ones that, when missing, stop the job on day one.
1.Foundation certificate. Concrete strength results, anchor position survey and the designer's sign-off. Erection on an uncured or mis-set foundation is the most expensive mistake in the sequence.
2.Site plan with crane positions. Including the mobile crane standing area, the exclusion zone and the transport vehicle route.
3.Component weight schedule. The heaviest single lift, at the radius it must be placed. This one number selects the mobile crane.
4.Wind forecast and the abort threshold. A three-day window with a defined stop rule, not a daily check.
5.Power availability. Temporary supply for the winch, the hydraulic climbing unit and lighting, at the right voltage.
6.Access and laydown. Where jib sections are assembled, and whether the ground can carry a 25 t trailer.
The component weight schedule is the input most often improvised. It should come from the manufacturer's shipping list, not from an estimate, because the difference between a 2.4 t and a 3.1 t jib section changes the mobile crane class.
Mobile Crane Selection
The mobile crane is the largest single cost line in erection and the one most often undersized. Selection is driven by the heaviest component, the radius at which it must be placed, and the boom length needed to reach the height.
|
Tower crane class |
Heaviest component |
Typical weight |
Mobile crane class |
Working radius |
|
QTZ63 / 5013 |
Turntable or jib root section |
3.5 - 4.5 t |
50 - 70 t |
12 - 18 m |
|
QTZ80 / 6015 |
Turntable with cab |
5.5 - 7 t |
70 - 100 t |
14 - 20 m |
|
6018 / 6515 |
Turntable and counter-jib |
6.5 - 8.5 t |
100 - 130 t |
16 - 22 m |
|
QTZ160 / 7020 |
Turntable and jib root |
8 - 11 t |
130 - 180 t |
18 - 24 m |
|
QTZ250 / 7527 |
Turntable and heavy jib section |
12 - 18 t |
200 - 300 t |
20 - 28 m |
|
Luffing jib |
Luffing jib root and A-frame |
10 - 16 t |
180 - 260 t |
18 - 26 m |
Two rules prevent most selection errors. First, use 75 percent of the mobile crane's published capacity at the actual radius, not 100 percent, because ground conditions and boom deflection consume margin. Second, confirm the boom length reaches the hook height with the load attached, not the height alone.
Ground bearing is the second half of the calculation. An outrigger load on soft ground can exceed 40 t, and a mat or steel plate is cheaper than a recovery operation.
Tower Crane Installation: The Assembly Sequence
The sequence below is typical for a flat-top crane erected with a mobile crane to free-standing height. Climbing to a higher working height follows as a separate operation.
|
Step |
Operation |
Duration |
Critical check |
|
1 |
Survey foundation, verify anchor positions |
2 h |
Position tolerance within 2 mm, concrete strength reached |
|
2 |
Install base section and levelling |
2 h |
Level within 1/1000 |
|
3 |
Assemble mast sections to free-standing height |
4 - 6 h |
Pin retention, section orientation, bolt torque |
|
4 |
Install climbing cage or hydraulic unit |
2 h |
Hose condition, pressure test |
|
5 |
Install slewing assembly and turntable |
3 h |
Slewing ring bolts to torque, grease charged |
|
6 |
Install operator cabin and electrical cabinet |
2 h |
Power isolation verified |
|
7 |
Assemble jib sections on the ground |
3 - 4 h |
Section numbering, pin fit, rope path |
|
8 |
Lift and pin the jib |
2 - 3 h |
Sling points per manual, wind under limit |
|
9 |
Install counter-jib and counterweight |
2 h |
Weight count and position match the load chart |
|
10 |
Reeve the hoist rope |
2 h |
Rope path, drum winding, rope end fixing |
|
11 |
Install limiters, anemometer, anti-collision |
3 h |
Two-stage limits, calibration |
|
12 |
No-load function test, then load test |
3 h |
Static and dynamic test per ISO 4310 |
Steps 7 and 8 are where most erection time is lost. Assembling jib sections on uneven ground produces pin misalignment, and correcting it after the jib is in the air is a two-hour job with a mobile crane on standby.
Climbing Versus Re-Erecting
When the building rises above the free-standing height, the crane must climb. The alternative - dismantling and re-erecting at a higher position - is occasionally cheaper on low-rise work and rarely cheaper above 60 m.
|
Criterion |
Climbing (telescoping) |
Dismantle and re-erect |
|
Typical duration |
1 day per climb cycle |
5 - 7 days |
|
Cost per cycle |
USD 1,500 - 4,000 |
USD 6,000 - 15,000 |
|
Crane downtime |
1 day |
5 - 7 days |
|
Structural risk |
Climbing loads on mast and guide |
Repetitive heavy lifts |
|
Requires |
Climbing frame, hydraulic unit, anchor ties |
Full mobile crane and crew again |
|
Best for |
Buildings above 60 m, regular floor cycles |
One-off repositioning, tight sites |
Climbing is a controlled operation with a defined sequence: install the climbing frame, balance the crane, release the slewing connection, telescope one section, pin, re-connect and re-calibrate. It is also the operation where the wind limit is most strictly applied, because a partly telescoped mast is the least stable configuration the crane will ever be in.
Anchoring is a related but separate activity. Wall ties are installed at intervals defined by the manufacturer, typically every 15 to 20 m of height, and each tie point needs a designed embedment or a through-bolt detail. Our notes on erecting a tower crane cover the structural preparation in more detail.
Wind Limits During Erection and Dismantling
Erection wind limits are stricter than operating limits, because the crane is in configurations it was never designed to hold in service.
|
Operation |
Typical limit |
Reason |
|
Mast section handling |
12 m/s |
Sail area of an unguided section |
|
Jib lift and pinning |
10 m/s |
Long, flexible load with high sail area |
|
Counter-jib and counterweight |
12 m/s |
Heavy lift, precise placement |
|
Climbing cycle |
10 m/s |
Partly telescoped mast is least stable |
|
Dismantling, jib removal |
10 m/s |
Corroded connections, unpredictable release |
|
Any operation with lightning risk |
Stop |
Personnel on the structure |
These are planning values. The manufacturer's manual overrides them for a specific model, and local regulation may be stricter. The practical rule is to define the abort threshold in the method statement and to give the supervisor the authority to stop without discussion.
Cost Breakdown and What Drives It
The erection budget has six lines, and buyers usually estimate only the first.
|
Cost line |
Typical range (USD) |
Driver |
|
Erection crew |
1,500 - 4,500 |
Crew size, days, local labour rates |
|
Mobile crane hire |
1,200 - 4,000 |
Crane class, days, mobilisation distance |
|
Climbing equipment |
500 - 1,500 |
Rental of climbing frame and hydraulic unit |
|
Electrical connection and testing |
400 - 1,200 |
Cable length, switchgear, certified electrician |
|
Load test weights and inspection |
500 - 2,000 |
Test load availability, third-party inspector |
|
Contingency |
10 - 15% of the total |
Weather, ground conditions, fit-up problems |
Responsibility Matrix: Who Owns What
Disputes at handover almost always trace to an unclear boundary. This matrix is worth attaching to the purchase contract.
|
Activity |
Buyer |
Supplier |
Erector |
|
Foundation design and construction |
Owns |
Advises on loads |
Verifies before erection |
|
Component delivery to site |
Receives |
Ships per term |
Unloads and checks |
|
Method statement and risk assessment |
Approves |
Provides technical input |
Authors and signs |
|
Mobile crane selection |
Approves |
Advises on weights |
Contracts and operates |
|
Erection and climbing |
Supervises |
May supply crew |
Executes |
|
Load test and handover |
Witnesses |
Provides procedure |
Performs and certifies |
|
Limiter calibration |
Receives certificate |
Supplies settings |
Calibrates |
|
Commissioning and operator training |
Attends |
Provides trainer |
Supports |